[66242] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. E25 - Air Handlers 1, 2, 3, 12 and Return Fan 3 Shutdown Re

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 2 14:39:49 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F2000@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ahatch@mit.edu'" <ahatch@mit.edu>, "'bengel@mit.edu'"
	 <bengel@mit.edu>,
        "'brig@med.mit.edu'" <brig@med.mit.edu>,
        "'dreid@mit.edu'" <dreid@mit.edu>, E-Zone <E-Zone@mit.edu>,
        "'elworthi@mit.edu'" <elworthi@mit.edu>,
        "'graposa@MIT.EDU'"
	 <graposa@mit.edu>,
        "'hegarty@mit.edu'" <hegarty@mit.edu>,
        "'jmganno@mit.edu'" <jmganno@mit.edu>,
        "'jrauch@mit.edu'"
	 <jrauch@mit.edu>,
        "'loudib@mit.edu'" <loudib@mit.edu>,
        "'mjudge@mit.edu'" <mjudge@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'sdalton@mit.edu'" <sdalton@mit.edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
        "'tquinn@mit.edu'"
	 <tquinn@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 2 Jun 2003 14:39:44 -0400 

> To: 	ahatch@mit.edu; bengel@mit.edu; brig@med.mit.edu; dreid@mit.edu;
> E-Zone; elworthi@mit.edu; graposa@MIT.EDU; hegarty@mit.edu;
> jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu; mjudge@mit.edu;
> schedule@mit.edu; sdalton@mit.edu; sdl-adm-lib@mit.edu; tquinn@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E25 - Air Handlers 1, 2, 3, 12 and Return Fan 3
> Shutdown Request
> 
> 
The following Air Handlers 1, 2, 3, 12 and Return 3 shutdown request for
Bldg. E25 on Saturday, June 7 is for your review and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: E25 
> Date: 6/7/2003
> Day: Saturday
> Time: 10 AM - 2 PM
> System: Air Handlers 1, 2, 3, 12 and Return Fan 3
> Duration: 4 hours
> Reason: 
> To clean intakes and perform preventive maintenance work on the
> above-listed fans. 
> 
> Effect: 
> Loss of supply ventilation, supply cooling, suppply heating as follows:
> Air Handler 1- services Northeast Labs - floors 2 thru 6 - low even
> numbered rooms;  Air Handler 2 services Southeast Labs on floors 2 thru 6
> - low odd numbered rooms;  Air Handler 3 services floors 1 through 6 -
> East End and Lecture Hall 3;  Air Handler 12 services East Hood Make-Up
> Air and Return Fan 3 - is a Return/Exhaust fan to Air Handler 3 during the
> 4-hour shutdown period.  Each Fan will be down one at a time while the
> other fans remain operational.
> 
> 

home help back first fref pref prev next nref lref last post