[66239] in Hotline Meeting
Bldg. E23 - Air Handlers 8, 9, 10, 11, Return Fans 8 and 9 Shutdo
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 2 14:00:54 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F1FFD@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@mit.edu>,
"'brig@med.mit.edu'"
<brig@med.mit.edu>,
"'dwye@med.mit.edu'" <dwye@med.mit.edu>,
"'fris@med.mit.edu'" <fris@med.mit.edu>,
"'tquinn@mit.edu'"
<tquinn@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 2 Jun 2003 14:00:43 -0400
> To: bengel@mit.edu; brig@med.mit.edu; dwye@med.mit.edu;
> fris@med.mit.edu; tquinn@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E23 - Air Handlers 8, 9, 10, 11, Return Fans 8 and 9
> Shutdown Request
>
>
The following Air Handlers 8, 9, 10, 11, Return Fans 8 and 9 shutdown
request for Bldg. E23 on Saturday, June 7 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E23
> Date: 6/7/2003
> Day: Saturday
> Time: 6 AM - 10 AM
> System: Air Handlers 8, 9, 10, 11, Return Fans 8 and 9
> Duration: 4 hours
> Reason:
> To clean intakes for the fans listed above and also perform preventive
> maintenance work on them.l
>
> Effect:
> Loss of supply ventilation (air from outside), supply cooling, supply
> heating to Air Handler 8 (services River end rooms on floors 1 through 3;
> Air Handler 9 services the Center of the building - floors 1 through 4;
> Air Handler 10 services the Hospital and Atrium areas; Air Handler 11
> services the North end floors 1 through 5 and Basement;, Return Fan 8
> supplies the return/exhaust general air for Air Handler 8 and Return Fan 9
> supplies the return/exhaust general air to Air Handler 9.
>
>