[66183] in Hotline Meeting
Bldg. 10 - Asbestos Removal Notification Only
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 29 10:49:24 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F1FC7@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aruspice@mit.edu'" <aruspice@mit.edu>, C-Zone <C-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dhelman@mit.edu'" <dhelman@mit.edu>,
"'emmarogers@mit.edu'"
<emmarogers@mit.edu>,
"'esdeb@mit.edu'" <esdeb@mit.edu>, "'fin@mit.edu'"
<fin@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'graposa@MIT.EDU'" <graposa@mit.edu>,
"'jhlyons@mit.edu'"
<jhlyons@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>, "'lkn@mit.edu'" <lkn@mit.edu>,
"'lsandler@mit.edu'" <lsandler@mit.edu>, "'lsc@mit.edu'" <lsc@mit.edu>,
"'marsha5@mit.edu'" <marsha5@mit.edu>,
"'mdhinkle@mit.edu'"
<mdhinkle@mit.edu>,
"'mleen@mit.edu'" <mleen@mit.edu>, "'ndk@mit.edu'"
<ndk@mit.edu>,
"'rrhonda@mit.edu'" <rrhonda@mit.edu>,
"'ryan@mit.edu'"
<ryan@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'tr6@mit.edu'" <tr6@mit.edu>, "'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"Patrick O'Toole" <pjotoole@PLANT.MIT.EDU>,
"'dcosta@mit.edu'"
<dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>,
Operators <Operators@PLANT.MIT.EDU>
Date: Thu, 29 May 2003 10:49:00 -0400
> To: aruspice@mit.edu; C-Zone; Cust-Coach; dfucillo@mit.edu;
> dhelman@mit.edu; emmarogers@mit.edu; esdeb@mit.edu; fin@mit.edu;
> granvill@mit.edu; graposa@MIT.EDU; jhlyons@mit.edu; jobrien@mit.edu;
> kates@mit.edu; lkn@mit.edu; lsandler@mit.edu; lsc@mit.edu;
> marsha5@mit.edu; mdhinkle@mit.edu; mleen@mit.edu; ndk@mit.edu;
> rrhonda@mit.edu; ryan@mit.edu; shutdowns@mit.edu; tr6@mit.edu;
> jdoucett@mit.edu; Patrick O'Toole; dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer;
> Operators
> Subject: Bldg. 10 - Asbestos Removal Notification Only
>
>
The following asbestos removal notification only for Bldg. 10 - 105 on
Monday, 6/9 through Friday, 6/13 is for your information. If you have any
questions about this, please contact Pat O'Toole at x3-7743.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 10 - 105
> Date: 6/9/2003
> Day: Monday
> Time: 7 AM (6/9) - 3 PM (6/13)
> System: None - asbestos removal notification only
> Duration: 5 days
> Reason:
> Must remove 250 linear feet of pipe insulation and 1,925 square feet of
> vat and mastic flooring.
>
> Effect:
> No access to 10-105 during the asbestos removal period.
>
>