Bldg. 6 - Rescheduled Air Handlers 1 and 2 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 28 10:38:26 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F1FA8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'chemistryhq@mit.edu'" <chemistryhq@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'khewitt@mit.edu'"
<khewitt@MIT.Edu>,
"'mhankin@mit.edu'" <mhankin@MIT.Edu>,
"'rhasselt@MIT.EDU'" <rhasselt@MIT.Edu>,
"'rjwilk@mit.edu'"
<rjwilk@MIT.Edu>,
"'rrdasari@mit.edu'" <rrdasari@MIT.Edu>,
"'saraf@mit.edu'" <saraf@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'serotek@mit.edu'" <serotek@MIT.Edu>,
"'heatherg@mit.edu'" <heatherg@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 28 May 2003 10:38:20 -0400
Dear Everyone:
Through no fault of our own - the shutdown for Bldg. 6 - floors 3 and 4
North and 3 and 4 South for this morning, Wednesday, 5/28 from 7 AM to 12
Noon did not occur. We would like to try again tomorrow, Thursday, 5/29 for
the same time period. Once again this would affect Air Handlers 1 and 2
(loss of supply ventilation (air from outside), supply cooling and supply
heating (via ceiling supply fans) on floors 3 and 4 only during the 5-hour
shutdown period.
Would you please be kind enough to let me know whether this does or does not
have your approval by 1 PM today, if possible.
Thank you again for your time and I look forward to hearing from you.
Andrea Nichols
Repair and Maintenance
8-7872