Bldg. 42 - Air Handler 1 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 22 13:44:16 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F1F57@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: George Mac Leod <gmacleod@mit.edu>, D-Zone <D-Zone@mit.edu>,
        "'hallisey@mit.edu'" <hallisey@mit.edu>,
        "'mcgrath@mtl.mit.edu'"
	 <mcgrath@mtl.mit.edu>,
        "'safety@mit.edu'" <safety@mit.edu>, "'armay@mit.edu'" <armay@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 22 May 2003 13:44:10 -0400

> To: 	George Mac Leod; D-Zone; hallisey@mit.edu; mcgrath@mtl.mit.edu;
> safety@mit.edu; armay@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 42 - Air Handler 1 Shutdown Request
> 
> 
The following air handler shutdown request for Bldg. 42 on Wednesday, 5/28
is for your nformation and comment.  Would you please let me know whether
this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 42
> Date: 5/28/2003
> Day: Wednesday
> Time:  7 AM - 12 Noon
> System: Air Handler 1/supply ventilation, supply cooling
> Duration: 5 hours
> Reason: 
> Controls systems upgrade.
> 
> Effect: 
> Loss of supply ventilation and supply cooling (via ceiling supply fans) in
> Bldg. 42 during the 5-hour shutdown period.
> 
> 