[66033] in Hotline Meeting
Bldg. W89 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 20 15:20:21 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F1F21@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Laura Lucas <LLucas@PLANT.MIT.EDU>,
Lisa StCroix
<LStCroix@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
D-Zone
<D-Zone@mit.edu>
Date: Tue, 20 May 2003 15:20:16 -0400
> To: Laura Lucas; Lisa StCroix; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; D-Zone
> Subject: Bldg. W89 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. W89 on Wednesday,
5/28 is for your review and comment. Would you please let me know whether
this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: W89
> Date: 5/28/2003
> Day: Wednesday
> Time: 5 AM - 7 AM
> System: Building Power
> Duration: 2 hours
> Reason:
> Add additional bus bar fingers for installation of new breaker for new air
> conditioning units.
>
> Effect:
> Loss of access controls (receptacles in offices), building power,
> computers, telephones, lighting in the corridors/stairs, supply
> ventilation, supply cooling, suply heating (via ceiling supply fans) and
> the fire alarm system during the 2-hour shutdown period. Should an
> emergency occur during the shutdown period, please dial either x100 or
> FIXIT (x3-4948) to report it. Thank you.
>
>