[66030] in Hotline Meeting
Bldg. 26 - Fire Protection Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 20 14:07:04 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F1F1D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'dudley@mit.edu'" <dudley@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'ljtrudel@mit.edu'"
<ljtrudel@MIT.Edu>,
"'lsc@mit.edu'" <lsc@MIT.Edu>, "'mhankin@mit.edu'"
<mhankin@MIT.Edu>,
"'nsteele@mit.edu'" <nsteele@MIT.Edu>,
"'safety@mit.edu'" <safety@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 20 May 2003 14:01:54 -0400
> To: amcgurl@rle.mit.edu; B-Zone; Cust-Coach; dudley@mit.edu;
> khewitt@mit.edu; ljtrudel@mit.edu; lsc@mit.edu; mhankin@mit.edu;
> nsteele@mit.edu; safety@mit.edu; schedule@mit.edu; wrgibbs@rle.mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 26 - Fire Protection Water Shutdown Request
>
>
The followng fire protection water shutdown request for Bldg. 26 on
Wednesday, 5/28 is for your information and comment. Would you please let
me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 26 - all
> Date: 5/28/2003
> Day: Wednesday
> Time: 7:30 AM - 2:30 PM
> System: Fire Protection Water
> Duration: 7 hours
> Reason:
> Relocate sprinkler heads in 26-268.
>
> Effect:
> Loss of fire protection water in Bldg. 26. The Safety Office will be
> advised of this - that office will notify the Fire Department.
>
>