[62450] in Hotline Meeting
Bldg. 26 - Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 15 09:58:00 2002
Message-ID: <568F0AEE7A57D511923900508B556451012329F2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'dudley@mit.edu'" <dudley@MIT.Edu>, "'kates@mit.edu'" <kates@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'ljtrudel@mit.edu'"
<ljtrudel@MIT.Edu>,
"'lsc@mit.edu'" <lsc@MIT.Edu>, "'mhankin@mit.edu'"
<mhankin@MIT.Edu>,
"'nsteele@mit.edu'" <nsteele@MIT.Edu>,
"'safety@mit.edu'" <safety@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'trobins@mit.edu'" <trobins@MIT.Edu>,
"'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 15 Nov 2002 09:57:42 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; dudley@mit.edu; kates@mit.edu; khewitt@mit.edu;
> ljtrudel@mit.edu; lsc@mit.edu; mhankin@mit.edu; nsteele@mit.edu;
> safety@mit.edu; schedule@mit.edu; trobins@mit.edu; wrgibbs@rle.mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 26 - Heating Hot Water Shutdown Request
>
>
The following heating hot water shutdown request for Bldg. 26 - 440 and rest
of the building on Monday, 11/18 is for your review and comment. Would you
please let me know whethe this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 26 - 440 and rest of the building
> Date: 11/18/2002
> Day: Monday
> Time: 6:30 AM - 9 AM
> System: heating hot water
> Duration: 2 1/2 hours
> Reason:
> Install control valve.
>
> Effect:
> Loss of heating hot water in Bldg. 26 during the early morning 2 2/1 hour
> shutdown period.
>
>