[62429] in Hotline Meeting
Bldg. 48 - Revised Air Handler/Supply Fan 5 Shutdown/Filter Chang
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 14 14:54:13 2002
Message-ID: <568F0AEE7A57D511923900508B556451012329E6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'hlbroder@mit.edu'" <hlbroder@MIT.Edu>,
"'mistetri@mit.edu'"
<mistetri@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sfrankel@mit.edu'" <sfrankel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 14 Nov 2002 14:53:52 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; hlbroder@mit.edu; mistetri@mit.edu;
> schedule@mit.edu; sfrankel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 48 - Revised Air Handler/Supply Fan 5 Shutdown/Filter
> Change Request
>
>
The following revised air handler/supply fan 5 shutdown/filter change
request for Bldg. 48 - 412 thru 438 (even #s) and 324 on Wednesday, 11/20 is
for your information and comment. Would you please let me know whether this
does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 48 - 412 thru 438 (even #s) and 324
> Date: 11/20/2002
> Day: Wednesday
> Time: 10 AM - 12 Noon
> System: Air Handler/Supply Fan 5 - PM#713036
> Duration: 2 hours
> Reason:
> Filter Changes.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in the
> above-listed rooms during the 2-hour shutdown/filter change period.
>
>