Bldg. 14S - Air Handler/Supply Fan 4 Shutdown Request/Filter Chan

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 12 08:32:46 2002

Message-ID: <568F0AEE7A57D511923900508B556451012329A2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
        "'cpomieko@mit.edu'" <cpomieko@MIT.Edu>,
        "'csnyder@mit.edu'"
	 <csnyder@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>,
        "'edorsch@mit.edu'"
	 <edorsch@MIT.Edu>,
        "'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
        "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
        "'jhlyons@mit.edu'"
	 <jhlyons@MIT.Edu>,
        "'jmullins@mit.edu'" <jmullins@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
        "'nlowe@mit.edu'"
	 <nlowe@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.Edu>,
        "'susanne@mit.edu'"
	 <susanne@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 12 Nov 2002 08:32:40 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; altenb@mit.edu; cpomieko@mit.edu; csnyder@mit.edu;
> Cust-Coach; edorsch@mit.edu; ellertsn@mit.edu; graposa@MIT.EDU;
> jhlyons@mit.edu; jmullins@mit.edu; shutdowns@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; susanne@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14S - Air Handler/Supply Fan 4 Shutdown Request/Filter
> Change
> 
> 
The following Air Handler/Supply Fan 4 shutdown request/filter change for
Bldg. 14S "West Half of the South Wing" on Monday, 11/18 is for your review
and comment.  Would you please let me know whether this does or does not
meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 14S - West Half of the South Wing
> Date: 11/18/2002
> Day: Monday
> Time: 1 PM - 3 PM
> System: Air Handler/Supply Fan 4 - PM#701223
> Duration: 2 hours
> Reason: 
> Bag filter changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentioned areas during the 2 hour shutdown request/filter change
> period.
> 
> 