[62330] in Hotline Meeting
RE: Case 321723: Bldg. 68 - Emergency Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 8 12:55:00 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232995@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'hotline@MIT.EDU'" <hotline@MIT.EDU>
Date: Fri, 8 Nov 2002 12:54:52 -0500
MIME-Version: 1.0
Content-Type: text/plain
Thanks Lou - but it isn't with John Fucillo - this will be sent out again
when I have different information.
Have a great weekend!
Andrea
-----Original Message-----
From: hotline@MIT.EDU [mailto:hotline@MIT.EDU]
Sent: Friday, November 08, 2002 12:53 PM
To: andrea@PLANT.MIT.EDU
Subject: Case 321723: Bldg. 68 - Emergency Power Shutdown Request
o.k. 1410,
--Lou
[11/08/2002 12:52:41 larugsi Comment]
===========================================================
Please retain the case reference in the subject line for future replies
associated with this case
Case History
==================
11/08/2002 9:04:12 daemon Email Received
Date: Fri, 8 Nov 2002 09:04:02 -0500
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'jfucillo@mit.edu'" <jfucillo@MIT.Edu>, "'jmganno@mit.edu'"
<jmganno@MIT.Edu>, "'maureen@mit.edu'" <maureen@MIT.Edu>,
"'rberlin@mit.edu'" <rberlin@MIT.Edu>, "'wganger@mit.edu'"
<wganger@MIT.Edu>, "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Subject: Bldg. 68 - Emergency Power Shutdown Request
> To: A-Zone; Cust-Coach; jfucillo@mit.edu; jmganno@mit.edu;
> maureen@mit.edu; rberlin@mit.edu; wganger@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 68 - Emergency Power Shutdown Request
>
>
The following emergency power shutdown request for Bldg. 68 - Floors 2 thru
6 North on Monday, 11/18, Tuesday, 11/19 and Wednesday, 11/20 is for your
review and comment. Would you please let me know whether this does or does
not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 68 - Floors 2 thru 6 North
> Date: 11/18/2002
> Day: Monday
> Time: 7:30 AM - 11 AM and 11 AM - 2:30 PM
> System: Emergency Power
> Duration: 3 days at 3 1/2 hours per floor
> Reason:
> Demo existing outlets; refeed for closet renovations; Flrs. 2 (7:30 AM -
> 11 AM) & 3 (11 AM - 2:30 PM) on 11/18, Flrs. 4 (7:30 AM - 11 AM) and 5 (11
> AM - 2:30 PM) on 11/19 and 6 (7:30 AM - 11 AM) on 11/20.
>
> Effect:
> Loss of emergency power in building - two floors at a time until 11/20
> where the 6th floor emergency power will be down.
>
>
11/08/2002 12:52:41 larugsi Comment
o.k. 1410,
--Lou
11/08/2002 12:52:41 larugsi Closed Case