Bldg. 18 - Approved Chilled Water Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 4 11:41:06 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123292E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'crendog@mit.edu'" <crendog@mit.edu>,
Gerry Desmond
<gdesmond@PLANT.MIT.EDU>,
Joe Collins <JCollins@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>, A-Zone <A-Zone@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Date: Mon, 4 Nov 2002 11:40:59 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: crendog@mit.edu; Gerry Desmond; Joe Collins
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer; A-Zone;
> shutdowns@mit.edu
> Subject: Bldg. 18 - Approved Chilled Water Shutdown
>
>
The following approved chilled water shutdown for Bldg. 18 on Tuesday, 11/12
through Friday, 12/13 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 18
> Date: 11/12/2002
> Day: Tuesday
> Time: 6 AM (11/12) - 2 PM (12/13)
> System: Chilled Water/Supply Cooling
> Duration: 33 days
> Reason:
> Replace 8" piping with 10 " piping.
>
> Effect:
> Loss of chilled water (air conditioning) and supply cooling (via ceiling
> supply fans) during the 33-day shutdown period.
>
>