[62221] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 35 - Emergency Electrical Power Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 4 10:55:50 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232929@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Eupremio Piccinonno <Eupremio@PLANT.MIT.EDU>,
        RM-ElecCtl
	 <rm-elecctl@mit.edu>, B-Zone <B-Zone@mit.edu>,
        Cust-Coach
	 <cust-coach@mit.edu>,
        "'gallant@mit.edu'" <gallant@mit.edu>,
        "'shtudowns@mit.edu'" <shtudowns@mit.edu>,
        "'gerwent@mit.edu'"
	 <gerwent@mit.edu>,
        "'inslee@mit.edu'" <inslee@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'stiffler@mit.edu'"
	 <stiffler@mit.edu>,
        Kevin Doran <kdoran@PLANT.MIT.EDU>,
        "'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>
Date: Mon, 4 Nov 2002 10:52:11 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	Eupremio Piccinonno; RM-ElecCtl; B-Zone; Cust-Coach;
> gallant@mit.edu; shutdowns@mit.edu; gerwent@mit.edu; inslee@mit.edu;
> schedule@mit.edu; stiffler@mit.edu; Kevin Doran; dcosta@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: 	Bldg. 35 - Emergency Electrical Power Shutdown
> 
> 
The following emergency electrical power shutdown for Blg. 35 - 3rd floor,
rooms, 333, 333A and 333B on Monday, 11/4 is for your information.  If you
have any questions about this, please contact Steve Gilligan at x3-8079.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Emergency
> Building: 35 - 3rd floor, rooms 333, 333A and 333B
> Date: 11/4/2002
> Day: Monday
> Time: 11 AM - 2 PM
> System: Electric Panel
> Duration: 3 hours
> Reason: 
> Need to replace feed wires as soon as possible.
> 
> Effect: 
> Loss of building power (receptacles in the above-listed rooms that affect
> computers, copy machines, fax machines, etc.) and lighting during the
> emergency 3-hour shutdown period.
> 
> 