[62159] in Hotline Meeting
Bldg. 26 - Approved Sanitary Drainage Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 31 08:40:33 2002
Message-ID: <568F0AEE7A57D511923900508B556451012328FA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Stephen Robinson <srobinso@PLANT.MIT.EDU>,
RM-PipeSys
<rm-pipesys@mit.edu>,
"'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>, "'dudley@mit.edu'" <dudley@mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>,
"'khewitt@mit.edu'" <khewitt@mit.edu>,
"'ljtrudel@mit.edu'"
<ljtrudel@mit.edu>,
"'lsc@mit.edu'" <lsc@mit.edu>, "'mhankin@mit.edu'"
<mhankin@mit.edu>,
"'nsteele@mit.edu'" <nsteele@mit.edu>,
"'safety@mit.edu'" <safety@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'trobins@mit.edu'" <trobins@mit.edu>,
"'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>
Date: Thu, 31 Oct 2002 08:40:12 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: Stephen Robinson; RM-PipeSys; amcgurl@rle.mit.edu; B-Zone;
> Cust-Coach; dudley@mit.edu; kates@mit.edu; khewitt@mit.edu;
> ljtrudel@mit.edu; lsc@mit.edu; mhankin@mit.edu; nsteele@mit.edu;
> safety@mit.edu; schedule@mit.edu; trobins@mit.edu; wrgibbs@rle.mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; johnnyd@mit.edu
> Subject: Bldg. 26 - Approved Sanitary Drainage Shutdown
>
>
The following approved sanitary drainage shutdown for Bldg. 26 - 328 only on
Monday, 11/4 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 26 - 328 only
> Date: 11/4/2002
> Day: Monday
> Time: 7 AM - 12 Noon
> System: Sanitary Drainage
> Duration: 5 hours
> Reason:
> To change-out broken pipe.
>
> Effect:
> Loss of sanitary drainage only in 26 - 328 during the shutdown period.
>
>