Bldg. E25 - Asbestos Removal Notification Only
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 30 14:31:28 2002
Message-ID: <568F0AEE7A57D511923900508B556451012328EE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ahatch@mit.edu'" <ahatch@mit.edu>, "'arolle@mit.edu'"
<arolle@mit.edu>,
"'bengel@mit.edu'" <bengel@mit.edu>,
"'brig@med.mit.edu'" <brig@med.mit.edu>,
"'cpoon@mit.edu'"
<cpoon@mit.edu>, "'dreid@mit.edu'" <dreid@mit.edu>,
E-Zone
<E-Zone@mit.edu>, "'elworthi@mit.edu'" <elworthi@mit.edu>,
"'graposa@MIT.EDU'" <graposa@mit.edu>,
"'hegarty@mit.edu'"
<hegarty@mit.edu>,
"'jmganno@mit.edu'" <jmganno@mit.edu>,
"'jrauch@mit.edu'" <jrauch@mit.edu>,
"'loudib@mit.edu'" <loudib@mit.edu>,
"'mjudge@mit.edu'" <mjudge@mit.edu>, "'rfink@mit.edu'" <rfink@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdalton@mit.edu'"
<sdalton@mit.edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
"'tquinn@mit.edu'" <tquinn@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'kurts@mit.edu'" <kurts@mit.edu>, "'tr6@mit.edu'"
<tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>,
Operators <Operators@PLANT.MIT.EDU>
Date: Wed, 30 Oct 2002 14:31:21 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: ahatch@mit.edu; arolle@mit.edu; bengel@mit.edu; brig@med.mit.edu;
> cpoon@mit.edu; dreid@mit.edu; E-Zone; elworthi@mit.edu; graposa@MIT.EDU;
> hegarty@mit.edu; jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu;
> mjudge@mit.edu; rfink@mit.edu; schedule@mit.edu; sdalton@mit.edu;
> sdl-adm-lib@mit.edu; tquinn@mit.edu; shutdowns@mit.edu; kurts@mit.edu;
> tr6@mit.edu; jdoucett@mit.edu; dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer;
> Operators
> Subject: Bldg. E25 - Asbestos Removal Notification Only
>
>
The following asbestos removal notification only for Bldg. E25 - 421B, 425
and 429 on Tuesday, 11/12 AM through Friday, 11/15 PM is for your
information. If you have any question about this, please contact Kurt
Samuelson at x8-5962.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E25 - 421B, 425 and 429
> Date: 11/12/2002
> Day: Tuesday
> Time: 7 AM (11/12) - 3 PM (11/15)
> System: None - asbestos removal notification only
> Duration: 4 days
> Reason:
> Must remove approximately 1,200 square feet of floor tile and 350 square
> feet of lab benches (both mastic) total in the above-listed rooms.
>
> Effect:
> No access to E25 - 421B, 425 ad 429 during the asbestos removal period.
>
>