[61954] in Hotline Meeting
Bldg. 24 - Normal Electric Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 21 09:08:42 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232858@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, "'cschultz@mit.edu'" <cschultz@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'dcairns@mit.edu'" <dcairns@MIT.Edu>,
"'devries@mit.edu'" <devries@MIT.Edu>,
"'dianajoy@mit.edu'"
<dianajoy@MIT.Edu>,
"'dturn@mit.edu'" <dturn@MIT.Edu>, "'esico@mit.edu'"
<esico@MIT.Edu>,
"'hallisey@mit.edu'" <hallisey@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'opsnote@mit.edu'"
<opsnote@MIT.Edu>,
"'pbrenton@MIT.EDU'" <pbrenton@MIT.Edu>,
"'politano@mit.edu'" <politano@MIT.Edu>,
"'pszenny@mit.edu'"
<pszenny@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sfalconi@mit.edu'" <sfalconi@MIT.Edu>,
"'wendell@mit.edu'"
<wendell@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 21 Oct 2002 09:08:34 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; cschultz@mit.edu; Cust-Coach; dcairns@mit.edu;
> devries@mit.edu; dianajoy@mit.edu; dturn@mit.edu; esico@mit.edu;
> hallisey@mit.edu; khewitt@mit.edu; opsnote@mit.edu; pbrenton@MIT.EDU;
> politano@mit.edu; pszenny@mit.edu; schedule@mit.edu; sfalconi@mit.edu;
> wendell@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 24 - Normal Electric Power Shutdown Request
>
>
The following normal electric power shutdown request for Bldg. 24 on Friday,
10/25 is for your information and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 24
> Date: 10/25/2002
> Day: Friday
> Time: 3 AM - 7 AM
> System: Normal Electric Power
> Duration: 4 hours
> Reason:
> To install electric meters.
>
> Effect:
> Loss of building power (receptacles), elevators, computers, lighting;
> Water: condenser water, Air: supply ventilation (air from outside),
> supply heating, exhaust-general and exhaust-toilet air during the 4-hour
> early morning shutdown period.
>
>