[61935] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg 24 fire alarm shutdown request for 10/22/02

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Oct 18 08:58:08 2002

Message-ID: <568F0AEE7A57D511923900508B55645101DBA8D2@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, cschultz@MIT.Edu,
        Cust-Coach
	 <cust-coach@MIT.Edu>, dcairns@MIT.Edu, devries@MIT.Edu,
        dianajoy@MIT.Edu, dturn@MIT.Edu, esico@MIT.Edu, hallisey@MIT.Edu,
        khewitt@MIT.Edu, opsnote@MIT.Edu, pbrenton@MIT.Edu, politano@MIT.Edu,
        pszenny@MIT.Edu, schedule@MIT.Edu, sfalconi@MIT.Edu, wendell@MIT.Edu,
        shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 18 Oct 2002 08:58:03 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; cschultz@mit.edu; Cust-Coach; dcairns@mit.edu;
> devries@mit.edu; dianajoy@mit.edu; dturn@mit.edu; esico@mit.edu;
> hallisey@mit.edu; khewitt@mit.edu; opsnote@mit.edu; pbrenton@MIT.EDU;
> politano@mit.edu; pszenny@mit.edu; schedule@mit.edu; sfalconi@mit.edu;
> wendell@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg 24 fire alarm shutdown request for 10/22/02
> 
> 
The following shutdown request is for building 24 on 10/22/02.  Please let
me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: 24 basement
> Date: 10/22/2002
> Day: Tuesday
> Time: 6 am - 7 am
> System: Fire alarms.  Live audible testing.
> Duration: 1 hour
> Reason: 
> Independent testing of the fire alarm system in the renovated area.
> 
> Effect: 
> The fire alarms will be down during this time.  There will also be live
> audible testing during this time.
> 
> 

home help back first fref pref prev next nref lref last post