Bldg. 48 - Chilled Water/Cold Lab Process Water & Supply Cooling

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 17 08:36:03 2002

Message-ID: <568F0AEE7A57D511923900508B5564510123283D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'hlbroder@mit.edu'" <hlbroder@MIT.Edu>,
        "'mistetri@mit.edu'"
	 <mistetri@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sfrankel@mit.edu'" <sfrankel@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 17 Oct 2002 08:36:00 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; hlbroder@mit.edu; mistetri@mit.edu;
> schedule@mit.edu; sfrankel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 48 - Chilled Water/Cold Lab Process Water & Supply
> Cooling Shutdown Request
> 
> 
The following chilled water/cold lab process water and supply cooling
shutdown request for Bldg. 48 on Saturday, 10/19 is for your information and
comment.  Would you please let me know whether this does or does not meet
with your approval.

Thank you.

Andrea Nichols
Repair and Maintennace
8-7872

> Status: Normal
> Building: 48
> Date: 10/19/2002
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Chilled Water/Cold lab Process Water and Supply Cooling
> Duration: 8 hours
> Reason: 
> Tie in Chilled Water line.
> 
> Effect: 
> Loss of chilled water (air conditioning) cold lab process water (for lab
> equipment) and supply cooling (via ceiling supply fans) in Bldg. 48 during
> the shutdown period.
> 
> 