[61813] in Hotline Meeting
Bldg. 48 - Hot/Cold Domestic/Lab Process and De-Ionized Water Shu
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 11 11:35:46 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123282F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'hlbroder@mit.edu'" <hlbroder@MIT.Edu>,
"'mistetri@mit.edu'"
<mistetri@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sfrankel@mit.edu'" <sfrankel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 11 Oct 2002 11:35:33 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; hlbroder@mit.edu; mistetri@mit.edu;
> schedule@mit.edu; sfrankel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 48 - Hot/Cold Domestic/Lab Process and De-Ionized
> Water Shutdown Request
>
>
The following hot/cold dometic/lab process and de-ionized water shutdown
request for Blg. 48 on Thursday, 10/17 PM to Friday, 10/18 AM is for your
review and comment. Would you please let me know wheher this does or does
not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
x8-7872
> Status: Normal
> Building: 48
> Date: 10/17/2002
> Day: Thursday
> Time: 9 PM (10/17) - 5 AM (10/18)
> System: Hot/Cold Domestic/Lab Process and De-ionized water
> Duration: 8 hours
> Reason:
> Reconnect new Vassar Street Water Main into Main Street
>
> Effect:
> Loss of hot/cold domestic water (no toilets, bathroom, kitchen, lab sink
> faucets or drinking fountains); possibly de-ionized water if tank runs out
> and hot/cold lab process water (affects equipment requiring use of same to
> be operational during the shutdown period.)
>
>