Bldg. 26 - Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 11 09:10:16 2002

Message-ID: <568F0AEE7A57D511923900508B5564510123282B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'dudley@mit.edu'" <dudley@MIT.Edu>,
        "'kates@mit.edu'" <kates@MIT.Edu>,
        "'khewitt@mit.edu'" <khewitt@MIT.Edu>,
        "'ljtrudel@mit.edu'" <ljtrudel@MIT.Edu>, "'lsc@mit.edu'" <lsc@MIT.Edu>,
        "'mhankin@mit.edu'" <mhankin@MIT.Edu>,
        "'nsteele@mit.edu'"
	 <nsteele@MIT.Edu>,
        "'safety@mit.edu'" <safety@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'trobins@mit.edu'"
	 <trobins@MIT.Edu>,
        "'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 11 Oct 2002 09:09:55 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	amcgurl@rle.mit.edu; B-Zone; Cust-Coach; dudley@mit.edu;
> kates@mit.edu; khewitt@mit.edu; ljtrudel@mit.edu; lsc@mit.edu;
> mhankin@mit.edu; nsteele@mit.edu; safety@mit.edu; schedule@mit.edu;
> trobins@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - Building Power Shutdown Request
> 
> 
The following building power shutdown request for Bldg. 26 - 033, 040, 043,
139, 140, 142, 143, 145, 237, 239, 240, 244 (Laser Area), 331, 340, 431,
433, 435, 437, 440, 441, 535, 537, 539, 540 and 541 on Saturday, 10/19 is
for your information and comment.  Would you please let me know whether this
does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 26- 033, 040, 043, 139, 140, 142, 143, 145, 237, 239, 240, 244,
> 331, 340, 431, 433, 435, 437, 440, 441, 535, 537, 539, 540 and 541
> Date: 10/19/2002
> Day: Saturday
> Time: 7:30 AM - 2:30 PM
> System: Building Power
> Duration: 7 hours
> Reason: 
> Replace existing power panel.
> 
> Effect: 
> Loss of building power, computers, receptacles for computers, copy
> machines, lighting and supply cooling, fan supply hood make-up air -
> PM#708460 for entire building, Air Conditioning unit - PM#705398 (Terminal
> Unit Fan Coil- Cooling) services 040; computer server in 340 (affects
> entire building).
> 
> 