Bldg. E15 - Rescheduled Air Handler Units 1, 4 and 6 Shutdown Req
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 10 14:42:35 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232827@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'barbra@media.mit.edu'" <barbra@media.mit.edu>, E-Zone
<E-Zone@MIT.Edu>,
"'haller@media.mit.edu'" <haller@media.mit.edu>,
"'heine@media.mit.edu'" <heine@media.mit.edu>,
"'kdavis@media.mit.edu'"
<kdavis@media.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 10 Oct 2002 14:42:29 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: barbra@media.mit.edu; E-Zone; haller@media.mit.edu;
> heine@media.mit.edu; kdavis@media.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E15 - Rescheduled Air Handler Units 1, 4 and 6
> Shutdown Request
>
>
The following rescheduled air handler units 1, 4 and 6 shutdown request for
Bldg. E15 - basement (except Bartos Theater), 1st, 2nd, 3rd and 4th floors
as well as the Gallery and Gallery Windows now on Thursday, 10/17 is again
for your information and comment. Would you please let me know whether this
does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E15 - basement (except Bartos Theater), 1st, 2nd, 3rd and 4th
> floors as well as the Gallery and Gallery Windows
> Date: 10/17/2002
> Day: Thursday
> Time: 6 AM - 10 AM
> System: Air Handler Units 1, 4, and 6
> Duration: 4 hours
> Reason:
> Control System Upgrade.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in the
> above-mentioned areas during the 4-hour shutdown period.
>
>