[61780] in Hotline Meeting
Bldg. 14 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 10 09:44:34 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123281D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
"'bkdavis@mit.edu'" <bkdavis@MIT.Edu>,
"'cpomieko@mit.edu'"
<cpomieko@MIT.Edu>,
"'csnyder@mit.edu'" <csnyder@MIT.Edu>,
Cust-Coach
<cust-coach@MIT.Edu>,
"'edorsch@mit.edu'" <edorsch@MIT.Edu>,
"'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
"'graposa@MIT.EDU'"
<graposa@MIT.Edu>,
"'jhlyons@mit.edu'" <jhlyons@MIT.Edu>,
"'jmullins@mit.edu'" <jmullins@MIT.Edu>,
"'mosh@mit.edu'" <mosh@MIT.Edu>, "'nlowe@mit.edu'" <nlowe@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.Edu>,
"'slarkin@mit.edu'" <slarkin@MIT.Edu>,
"'susanne@mit.edu'"
<susanne@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'tr6@mit.edu'" <tr6@MIT.Edu>, "'jdoucett@mit.edu'" <jdoucett@MIT.Edu>,
"'tdoyle@mit.edu'" <tdoyle@MIT.Edu>,
"'dcosta@mit.edu'" <dcosta@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Thu, 10 Oct 2002 09:43:34 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; altenb@mit.edu; bkdavis@mit.edu; cpomieko@mit.edu;
> csnyder@mit.edu; Cust-Coach; edorsch@mit.edu; ellertsn@mit.edu;
> graposa@MIT.EDU; jhlyons@mit.edu; jmullins@mit.edu; mosh@mit.edu;
> nlowe@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu;
> susanne@mit.edu; shutdowns@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu; dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. 14 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. 14 Monday, 10/21 is
for your information. If you have any questions about this, please contact
Tammy Doyle at x3-5166.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 14 - Basement Mechanical Room
> Date: 10/21/2002
> Day: Monday
> Time: 7 AM - 4 PM
> System: None - asbestos femoval notification
> Duration: 9 hours
> Reason:
> Must remove 3 square feet of floor tile in 14 - Basement Mechanical.
>
> Effect:
> No access to Bldg.14 Basement Mechanical room during the asbestos removal
> period.
>
>