Bldg. 12 - Compressed Lab Air Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 2 13:16:38 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232776@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'jbartels@MIT.EDU'" <jbartels@MIT.Edu>,
"'jcentor@mit.edu'"
<jcentor@MIT.Edu>,
"'momeara@mit.edu'" <momeara@MIT.Edu>,
"'rigione@mit.edu'" <rigione@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Date: Wed, 2 Oct 2002 13:16:34 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; jbartels@MIT.EDU; jcentor@mit.edu;
> momeara@mit.edu; rigione@mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu
> Subject: Bldg. 12 - Compressed Lab Air Shutdown Request
>
>
The following compressed lab air shutdown request for Bldg. 12 - on Tuesday,
10/8 is for your review and comment. Would you please let me know whether
this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 12
> Date: 10/8/2002
> Day: Tuesday
> Time: 7:30 AM - 10:30 AM
> System: Compressed Lab Air
> Duration: 3 hours
> Reason:
> Replace. Regulator off Main Air Line.
>
> Effect:
> Loss of compressed lab air during the 3-hour shutdown period.
>
>