Bldg. 66 - Hot/Cold Domestic/Lab Process Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 27 11:24:25 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232733@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'haverty@mit.edu'" <haverty@MIT.Edu>, "'kkg@mit.edu'" <kkg@MIT.Edu>,
"'swetzel@mit.edu'" <swetzel@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 27 Sep 2002 11:24:21 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; haverty@mit.edu; kkg@mit.edu; swetzel@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - Hot/Cold Domestic/Lab Process Water Shutdown
> Request
>
>
The following hot/cold domestic/lab process water shutdown request for Bldg.
66 on Tuesday, 10/1 is for your review and comment. Would you please let me
know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66
> Date: 10/1/2002
> Day: Tuesday
> Time: 5 AM - 6:30 AM
> System: Hot/Cold Domestic Water/Lab Process Water
> Duration: 1 1/2 hours
> Reason:
> Relocate hot/cold domestic water lines on 2nd floor for renovation.
>
> Effect:
> Loss of hot/cold domestic water (this means that no toilets, bathroom,
> kitchen, lab sink faucets or drinking fountains will be operational;
> hot/cold lab procss water this means that no lab equipment requiring use
> of same will not be operational during the 1 1/2 hour shutdown period.
>
>