[61492] in Hotline Meeting
Bldg. W5 - All Normal Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 24 10:02:35 2002
Message-ID: <568F0AEE7A57D511923900508B556451012326E1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'kcn@mit.edu'" <kcn@mit.edu>, "'mwhelan@mit.edu'" <mwhelan@mit.edu>,
"'bailey@mit.edu'" <bailey@mit.edu>,
"'opsnote@mit.edu'"
<opsnote@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 24 Sep 2002 10:02:30 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: kcn@mit.edu; mwhelan@mit.edu; bailey@mit.edu; opsnote@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. W5 - All Normal Power Shutdown Request
>
>
The following all nomal power shutdown request for Blg. W5 on Friday, 9/27
is for your information and comment. Would you please let me know whether
this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: W5
> Date: 9/27/2002
> Day: Friday
> Time: 11 AM - 2 PM
> System: All Normal Power
> Duration: 3 hours
> Reason:
> To install new electric meter, circuits and points.
>
> Effect:
> Loss of building power, elevators, telephones, lighting and supply
> ventilation during the 3-hour shutdown period.
>
>