[61299] in Hotline Meeting
Bldg. 24 - Chilled Water/Supply Cooling Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 12 14:53:49 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123261B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, "'cschultz@mit.edu'" <cschultz@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'dcairns@mit.edu'" <dcairns@MIT.Edu>,
"'devries@mit.edu'" <devries@MIT.Edu>,
"'dturn@mit.edu'" <dturn@MIT.Edu>, "'esico@mit.edu'" <esico@MIT.Edu>,
"'hallisey@mit.edu'"
<hallisey@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'opsnote@mit.edu'" <opsnote@MIT.Edu>,
"'politano@mit.edu'"
<politano@MIT.Edu>,
"'pszenny@mit.edu'" <pszenny@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sfalconi@mit.edu'"
<sfalconi@MIT.Edu>,
"'wendell@mit.edu'" <wendell@MIT.Edu>,
"'hbsweet@mit.edu'" <hbsweet@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 12 Sep 2002 14:53:43 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; cschultz@mit.edu; Cust-Coach; dcairns@mit.edu;
> devries@mit.edu; dturn@mit.edu; esico@mit.edu; hallisey@mit.edu;
> khewitt@mit.edu; opsnote@mit.edu; politano@mit.edu; pszenny@mit.edu;
> schedule@mit.edu; sfalconi@mit.edu; wendell@mit.edu; hbsweet@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 24 - Chilled Water/Supply Cooling Shutdown Request
>
>
The following chilled water/supply cooling shutdown request for Bldg. 24
entire building except 016 (Telecom) on Wednesday, 9/18 AM and Thursday,
9/19 AM is for your review and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 24 - all except 016
> Date: 9/18/2002
> Day: Wednesday
> Time: 5 AM - 11 AM each day
> System: Chilled Water and chilled water pumps.
> Duration: 2 days @ 6 hours each day
> Reason:
> Tie in chilled water to newly renovated area in low rise, remove partial
> loop.
>
>
> Effect:
> No cooling in Bldg during shutdown. Portable cooling devices will be
> provided for critical areas (032B and 027T). Room 016 already has DX units
> (Telecom).
>
>