[61264] in Hotline Meeting
Bldg. 48 - Air Handler 5 Short Interruptions
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 11 07:34:20 2002
Message-ID: <568F0AEE7A57D511923900508B556451012325F1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sfrankel@mit.edu'" <sfrankel@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 11 Sep 2002 07:34:16 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: sfrankel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 48 - Air Handler 5 Short Interruptions
>
>
The following notification for Bldg. 48 - 4th floor on Monday, 9/16 is for
your information. Air handler 5 will run all day with short interruptions
while the air distribution system is being balanced. If you have any
questions about this, please contact Warren Scott at x 3-6328.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 48 - 4th floor
> Date: 9/16/2002
> Day: Monday
> Time: 7 AM - 3 PM
> System: Air Handler 5
> Duration: 8 hours
> Reason:
> Balance air distribution system.
>
> Effect:
> Short interruptions of supply ventilation and supply cooling in Bldg. 48 -
> 4th floor during the shutdown period.
>
>