Bldg. 14 - Air Handler 4 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 10 10:38:31 2002

Message-ID: <568F0AEE7A57D511923900508B556451012325D8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'altenb@mit.edu'" <altenb@MIT.Edu>,
        "'cpomieko@mit.edu'" <cpomieko@MIT.Edu>,
        "'csnyder@mit.edu'"
	 <csnyder@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>,
        "'edorsch@mit.edu'"
	 <edorsch@MIT.Edu>,
        "'ellertsn@mit.edu'" <ellertsn@MIT.Edu>,
        "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
        "'jhlyons@mit.edu'"
	 <jhlyons@MIT.Edu>,
        "'jmullins@mit.edu'" <jmullins@MIT.Edu>,
        "'mosh@mit.edu'" <mosh@MIT.Edu>, "'nlowe@mit.edu'" <nlowe@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'"
	 <sdl-adm-lib@MIT.Edu>,
        "'slarkin@mit.edu'" <slarkin@MIT.Edu>,
        "'susanne@mit.edu'" <susanne@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 10 Sep 2002 10:38:19 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; altenb@mit.edu; cpomieko@mit.edu; csnyder@mit.edu;
> Cust-Coach; edorsch@mit.edu; ellertsn@mit.edu; graposa@MIT.EDU;
> jhlyons@mit.edu; jmullins@mit.edu; mosh@mit.edu; nlowe@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; slarkin@mit.edu; susanne@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14 - Air Handler 4 Shutdown Request
> 
> 
The following Air handler 2 shutdown request for Bldg. 14W - West half of
South Wing 1st and 2nd floors on Thursday, 9/12 is for your review and
comment.  Would you please let me know whether this does or does not met
with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872


> Status: Normal
> Building: 14W (West half or South Wing - 1st and 2nd floors)
> Date: 9/12/2002
> Day: Thursday
> Time: 7:30 AM - 11:30 AM
> System: Air Handler 4 - PM#701223
> Duration: 4 hours
> Reason: 
> Chilled water valve broken (need to inspect).
> 
> Effect: 
> Loss of supply ventilation and supply cooling in the above-listed areas
> during the shutdown period.
> 
> 