[61166] in Hotline Meeting
Bldg. 24 - All Steam/Condensate Return Shutdown Requet
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 6 12:57:11 2002
Message-ID: <568F0AEE7A57D511923900508B556451012325B9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, "'cschultz@mit.edu'" <cschultz@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'dcairns@mit.edu'" <dcairns@MIT.Edu>,
"'devries@mit.edu'" <devries@MIT.Edu>,
"'dturn@mit.edu'" <dturn@MIT.Edu>, "'esico@mit.edu'" <esico@MIT.Edu>,
"'hallisey@mit.edu'"
<hallisey@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'opsnote@mit.edu'" <opsnote@MIT.Edu>,
"'politano@mit.edu'"
<politano@MIT.Edu>,
"'pszenny@mit.edu'" <pszenny@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sfalconi@mit.edu'"
<sfalconi@MIT.Edu>,
"'wendell@mit.edu'" <wendell@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'opsnote@mit.edu'"
<opsnote@MIT.Edu>,
"'stringf@mit.edu'" <stringf@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 6 Sep 2002 12:56:58 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; cschultz@mit.edu; Cust-Coach; dcairns@mit.edu;
> devries@mit.edu; dturn@mit.edu; esico@mit.edu; hallisey@mit.edu;
> khewitt@mit.edu; opsnote@mit.edu; politano@mit.edu; pszenny@mit.edu;
> schedule@mit.edu; sfalconi@mit.edu; wendell@mit.edu; shutdowns@mit.edu;
> opsnote@mit.edu; stringf@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 24 - All Steam/Condensate Return Shutdown Requet
>
>
The following all steam/condensate return shutdown request for Bldg. 24 on
Thursday, 9/12 is for your information and comment. Would you please let me
know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 24
> Date: 9/12/2002
> Day: Thursday
> Time: 6:30 AM - 10:30 AM
> System: High, medium, low pressure steam/condensate return
> Duration: 4 hours
> Reason:
> Tie-in new High Pressure steam traps.
>
> Effect:
> Loss of all steam/condensate return. This means there will be no hot
> domestic water (for bathroom, kitchen and lab sink faucets) or building
> heating hot water during the shutdown period.
>
>