[61158] in Hotline Meeting
Bldg. 66 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 6 08:05:54 2002
Message-ID: <568F0AEE7A57D511923900508B556451012325A5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'haverty@mit.edu'" <haverty@MIT.Edu>,
"'kkgleasn@mit.edu'"
<kkgleasn@MIT.Edu>,
"'patsys@mit.edu'" <patsys@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'swetzel@mit.edu'"
<swetzel@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'tr6@mit.edu'" <tr6@MIT.Edu>, "'jdoucett@mit.edu'" <jdoucett@MIT.Edu>,
Tim Donaghey <TDonaghe@PLANT.MIT.EDU>,
"'dcosta@mit.edu'"
<dcosta@MIT.Edu>,
"'tdoyle@mit.edu'" <tdoyle@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Fri, 6 Sep 2002 08:05:48 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> patsys@mit.edu; schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu;
> tr6@mit.edu; jdoucett@mit.edu; Tim Donaghey; dcosta@mit.edu;
> tdoyle@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. 66 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. 66 - 353 on Monday,
9/9 trought Wednesday, 9/11 is for your information. If you have any
questions about this, please contact Tammy Doyle at X3-5166.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - 353
> Date: 9/9/2002
> Day: Monday
> Time: 9/9 (7 AM) - 9/11 (4 PM)
> System: None - asbestos removal notification only
> Duration: 57 hours
> Reason:
> Must remove 30 square feet of floor tile in 353.
>
> Effect:
> No access to 66 - 353 during the asbestos removal period.
>
>