[61116] in Hotline Meeting
Bldg 48 shutdown of AH5 rescheduled for 9/7/02
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Sep 4 08:58:27 2002
Message-ID: <568F0AEE7A57D511923900508B55645101B16D70@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, hlbroder@MIT.Edu,
mistetri@MIT.Edu, schedule@MIT.Edu, sfrankel@MIT.Edu,
shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 4 Sep 2002 08:58:19 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; hlbroder@mit.edu; mistetri@mit.edu;
> schedule@mit.edu; sfrankel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg 48 shutdown of AH5 rescheduled for 9/7/02
>
>
The following shutdown request for building 48 air handler 5 is being
rescheduled for September 7. Please let me know if this does or does not
meet with your approval.
Thank you
Dawn Simonelli]
Repair and Maintenance
> Status: Normal
> Building: 48 4th floor even numbered rooms.
> Date: 9/7/2002
> Day: Saturday
> Time: 7am - 11 am
> System: Air handler 5
> Duration: 4 hours
> Reason:
> Inspection and preventive maintenance for winter operation of OA dampers,
> freesze stats and F& B dampers.
>
> Effect:
> There will be no supply air ventilation or supply air cooling during this
> time.
>
>