Bldg 2 2nd &3rd floors chilled water shutdown request for 9/3

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Aug 30 12:01:54 2002

Message-ID: <568F0AEE7A57D511923900508B55645101B16CBE@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, capozzi@math.mit.edu, chemistryhq@MIT.Edu,
        Cust-Coach <cust-coach@MIT.Edu>, duggins@math.mit.edu, rjwilk@MIT.Edu,
        schedule@MIT.Edu, sdimond@MIT.Edu, serotek@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 30 Aug 2002 12:01:43 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; capozzi@math.mit.edu; chemistryhq@mit.edu; Cust-Coach;
> duggins@math.mit.edu; rjwilk@mit.edu; schedule@mit.edu; sdimond@mit.edu;
> serotek@mit.edu; shutdowns@Mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg 2 2nd &3rd floors chilled water shutdown request for
> 9/3
> 
> 
The following shutdown request is for building 2 for the second and third
floors on 9/3.  Please let me know if this does or does not meet with your
approval.

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: 2 second and third floors.
> Date: 9/3/2002
> Day: Tuesday
> Time: 7am - 11am
> System: Chilled water
> Duration: 4 hours
> Reason: 
> Tie in new fan coil units in room 235, 372 and 378.
> 
> Effect: 
> There will be a loss of chilled water during this time.
> 
> 