Bldg E23 Critical shutdown request for 9/2/02

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Aug 29 13:01:11 2002

Message-ID: <568F0AEE7A57D511923900508B55645101B16C4E@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, bengel@MIT.Edu, brig@med.mit.edu,
        dwye@med.mit.edu, fris@med.mit.edu, tquinn@MIT.Edu, schedule@MIT.Edu,
        shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 29 Aug 2002 13:01:05 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	E-Zone; bengel@mit.edu; brig@med.mit.edu; dwye@med.mit.edu;
> fris@med.mit.edu; tquinn@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg E23 Critical shutdown request for 9/2/02
> 
> 
The following critical shutdown request is for building E23 on 9/2/02.
Please let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Critical
> Building: E23
> Date: 9/2/2002
> Day: Monday
> Time: 7am - 3pm
> System: Domestic hot and Cold and all drain piping.
> Duration: 8 hours
> Reason: 
> To cut and cap water lines and change out some drainage in the basement.
> 
> Effect: 
> There will be no hot or cold domestic water available during this time.
> Also no hot or cold lab processed water during this time.
> 
> 