[61045] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 48 - Air Handler 5 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 29 10:25:40 2002

Message-ID: <568F0AEE7A57D511923900508B5564510123257F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'hlbroder@mit.edu'" <hlbroder@mit.edu>,
        "'mistetri@mit.edu'"
	 <mistetri@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'sfrankel@mit.edu'" <sfrankel@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 29 Aug 2002 10:25:31 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	hlbroder@mit.edu; mistetri@mit.edu; schedule@mit.edu;
> sfrankel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 48 - Air Handler 5 Shutdown Request
> 
> 
The following Air handler 5 shutdown request for Bldg. 48- 4th floor on
Wednesday, 9/4 is for your review and comment.  Would you please let me know
whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 48 - 4th floor
> Date: 9/4/2002
> Day: Wednesday
> Time: 7 AM - 11 AM
> System: Air Handler 5
> Duration: 4 hours
> Reason: 
> Inspectionand preventive maintenance work for winter operation/on O.A.
> dampers, freeze stats, and F & B dampers.
> 
> Effect: 
> Loss of supply ventilation and supply cooling in Bldg. 48 - 4th floor
> during the 4-hour shutdown period.
> 
> 