[60984] in Hotline Meeting
Bldg. 1 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 26 14:12:40 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232536@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Schedules Office <schedules@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 26 Aug 2002 14:12:32 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: Schedules Office; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 1 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 1 - All classrooms
around Rm. 246 on Tuesday, 8/27 is for your information and comment. Would
you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 1 - all classrooms around Rm. 246
> Date: 8/27/2002
> Day: Tuesday
> Time: 6 AM - 7 AM
> System: Bldg. Power
> Duration: 1 hour
> Reason:
> Tie in new switch gear.
>
> Effect:
> Loss of building power and computers in the above-mentioned areas during
> the 1-hour shutdown period.
>
>