Bldg. 1 - Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 26 14:12:40 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232536@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Schedules Office <schedules@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 26 Aug 2002 14:12:32 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	Schedules Office; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1 - Building Power Shutdown Request
> 
> 
The following building power shutdown request for Bldg. 1 - All classrooms
around Rm. 246 on Tuesday, 8/27 is for your information and comment.  Would
you please let me know whether this does or does not meet with your
approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 1 - all classrooms around Rm. 246
> Date: 8/27/2002
> Day: Tuesday
> Time: 6 AM - 7 AM
> System: Bldg. Power
> Duration: 1 hour
> Reason: 
> Tie in new switch gear.
> 
> Effect: 
> Loss of building power and computers in the above-mentioned areas during
> the 1-hour shutdown period.
> 
> 