[60817] in Hotline Meeting
Bldg. 18 - Rescheduled Electrical Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 15 11:38:31 2002
Message-ID: <568F0AEE7A57D511923900508B556451012324B7@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
"'serotek@mit.edu'"
<serotek@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 15 Aug 2002 11:38:19 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: rjwilk@mit.edu; serotek@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 18 - Rescheduled Electrical Power Shutdown Request
>
>
The following rescheduled electrical power shutdown request for Bldg. 18 -
X-Ray Lab now on Wednesday, 8/21 is again for your review and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 18 - X-Ray Lab (488X and 488A)
> Date: 8/21/2002
> Day: Wednesday
> Time: 6 AM - 2 PM
> System: Normal Power
> Duration: 8 hours
> Reason:
> To transfer from temporary electric feed to permanent.
>
> Effect:
> Loss of building power (access controls, computers, telephones and
> lighting) in Bldg. 18 - X-Ray Lab during the shutdown period.
>
>