[60791] in Hotline Meeting
Bldg. E18 - Air Handler/Supply Fan 10 Filter Change/Shutdown Requ
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 14 09:42:24 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232497@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wardd@mit.edu'" <wardd@mit.edu>, "'jmganno@mit.edu'"
<jmganno@mit.edu>,
"'sdalton@mit.edu'" <sdalton@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'nedivi@mit.edu'"
<nedivi@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
E-Zone
<E-Zone@mit.edu>
Date: Wed, 14 Aug 2002 09:42:21 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: wardd@mit.edu; jmganno@mit.edu; sdalton@mit.edu; shutdowns@mit.edu;
> nedivi@mit.edu
> Cc: shutdown@plant.mit.edu; E-Zone
> Subject: Bldg. E18 - Air Handler/Supply Fan 10 Filter Change/Shutdown
> Request
>
>
The following Air Handler/Supply Fan 10 Filter Change/Shutdown request for
Bldg. E18 on Friday, 8/16 is for your review and comment. Would you please
let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E18
> Date: 8/16/2002
> Day: Friday
> Time: 11 AM - 12:30 PM
> System: Air Handler/Supply Fan 10 - PM#730442
> Duration: 1 1/2 hours
> Reason:
> Bag filter changes.
>
> Effect:
> Minimal loss of supply ventilation, supply cooling and supply heating (not
> on in summer) during the 1 1/2 hour filter change/shutdown period. Air
> Handler/Supply Fans 8 and 9 will serve as back up units.
>
>