[60169] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 18 - Auxillary Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 2 09:43:45 2002

Message-ID: <568F0AEE7A57D511923900508B5564510123219B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
        "'serotek@mit.edu'"
	 <serotek@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 2 Jul 2002 09:43:34 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; serotek@mit.edu; shutdowns@mit.edu; opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 18 - Auxillary Power Shutdown Request
> 
> 
The following auxillary power shutdown request for Bldg. 18 - 244, 245 and
247 on Tuesday, July 9 is for your information and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 18 - 244, 245 and 247
> Date: 7/9/2002
> Day: Tuesday
> Time: 6 AM - 7 AM
> System: Auxillary Power
> Duration: 1 hour
> Reason: 
> To tie in first floor auxillary panel.
> 
> Effect: 
> Loss of building and auxillary power in Bldg. 18 - 244, 245 and 247. This
> means there will be no computers, telephones, lighting, access controls or
> air during the 1-hour shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post