[60167] in Hotline Meeting
Bldg. 34 - Rescheduled Supply Ventilation/Supply Cooling Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 2 09:07:41 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232199@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'rroscoe@mit.edu'" <rroscoe@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 2 Jul 2002 09:07:37 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; rroscoe@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 34 - Rescheduled Supply Ventilation/Supply Cooling
> Shutdown Request
>
>
The following rescheduled supply ventilation/supply cooling shutdown request
for Bldg. 34 is now for Monday, July 8. Would you please let me know if
this new date meets with your approval or does not.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 34
> Date: 7/8/2002
> Day: Monday
> Time: 7:30 AM - 3:30 PM
> System: HVAC/Supply ventilation/Supply Cooling
> Duration: 8 hours
> Reason:
> Control System upgrade.
>
> Effect:
> Loss of supply ventilation (fresh air from outside) and supply cooling
> (via ceiling supply fans) during the shutdown period.
>
>