[60130] in Hotline Meeting
Bldg. E32 - Chilled Water/Heating Hot Water/Supply Cooling/Heatin
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 27 15:04:47 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232162@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, "'jmcd@mit.edu'" <jmcd@MIT.Edu>,
"'lrbrutti@mit.edu'" <lrbrutti@MIT.Edu>,
"'mshenry@mit.edu'"
<mshenry@MIT.Edu>,
"'mwhelan@mit.edu'" <mwhelan@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 27 Jun 2002 15:04:44 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: E-Zone; jmcd@mit.edu; lrbrutti@mit.edu; mshenry@mit.edu;
> mwhelan@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E32 - Chilled Water/Heating Hot Water/Supply
> Cooling/Heating Shutdown Request
>
>
The following chilled water/heating hot water/supply cooling/supply heating
shutdown request for Bldg. E32 on Thursday, July 11 is for your review and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E32 - All
> Date: 7/11/2002
> Day: Thursday
> Time: 7:30 AM - 3:30 PM
> System: Chilled Water/Heating Hot Water
> Duration: 8 hours
> Reason:
> To fix boiler valves that are leaking by dumping chilled water.
>
> Effect:
> Loss of chilled water (air conditioning)/heating hot water (building heat)
> and supply cooling/supply heating (via ceiling supply fans) during the
> 8-hour shutdown period.
>
>