[60126] in Hotline Meeting
Bldg. N52 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 27 10:13:33 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232154@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'adavies@mit.edu'" <adavies@mit.edu>, "'aprg@mit.edu'" <aprg@mit.edu>,
"'arhodes@mit.edu'" <arhodes@mit.edu>, "'brux@mit.edu'" <brux@mit.edu>,
D-Zone <D-Zone@mit.edu>, "'dianan@mit.edu'" <dianan@mit.edu>,
"'emlayne@mit.edu'" <emlayne@mit.edu>,
"'hdebaun@mit.edu'"
<hdebaun@mit.edu>,
"'honda@mit.edu'" <honda@mit.edu>,
"'lgross@mit.edu'"
<lgross@mit.edu>,
"'loanet@mit.edu'" <loanet@mit.edu>,
"'mleen@mit.edu'"
<mleen@mit.edu>, "'ronnc@MIT.EDU'" <ronnc@mit.edu>,
"'sabenton@mit.edu'"
<sabenton@mit.edu>,
"'tmrc-officers@mit.edu'" <tmrc-officers@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
Dave Hingston
<dhingsto@PLANT.MIT.EDU>,
"'tr6@mit.edu'" <tr6@mit.edu>, "'jdoucett@mit.edu'" <jdoucett@mit.edu>,
Jack Allen
<jrallen@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>,
"'dcosta@mit.edu'" <dcosta@mit.edu>
Date: Thu, 27 Jun 2002 10:13:22 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: adavies@mit.edu; aprg@mit.edu; arhodes@mit.edu; brux@mit.edu;
> D-Zone; dianan@mit.edu; emlayne@mit.edu; hdebaun@mit.edu; honda@mit.edu;
> lgross@mit.edu; loanet@mit.edu; mleen@mit.edu; ronnc@MIT.EDU;
> sabenton@mit.edu; tmrc-officers@mit.edu; shutdowns@mit.edu; Dave Hingston;
> tr6@mit.edu; jdoucett@mit.edu; Jack Allen
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators;
> dcosta@mit.edu
> Subject: Bldg. N52 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. N52 - Boiler Room on
Monday, July 8 through Tuesday, July 9 is for your information. If you have
any questions about this, please contact Jack Allen at x3-6352.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: N52 - Boiler Room
> Date: 7/8/2002
> Day: Monday
> Time: 7 AM (7/8) - 4 PM (7/9)
> System: None - asbestos removal notification
> Duration: 33 hours
> Reason:
> Leaking roof drain. Must remove 10 linear feet of pipe insulation going
> down drain pipe.
>
> Effect:
> No access to N52 Boiler Room during the asbestos removal period.
>
>