[60091] in Hotline Meeting
Bldg. 12 - Bldg. Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 25 07:28:43 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123211F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bkaynor@mit.edu'" <bkaynor@mit.edu>, C-Zone <C-Zone@mit.edu>,
"'caferrar@mit.edu'" <caferrar@mit.edu>,
"'cgroves@mit.edu'"
<cgroves@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'granvill@mit.edu'"
<granvill@mit.edu>,
"'jbartels@MIT.EDU'" <jbartels@mit.edu>,
"'jcentor@mit.edu'" <jcentor@mit.edu>,
"'momeara@mit.edu'"
<momeara@mit.edu>,
"'rigione@mit.edu'" <rigione@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 25 Jun 2002 07:28:36 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: bkaynor@mit.edu; C-Zone; caferrar@mit.edu; cgroves@mit.edu;
> Cust-Coach; granvill@mit.edu; jbartels@MIT.EDU; jcentor@mit.edu;
> momeara@mit.edu; rigione@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 12 - Bldg. Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 12 on Saturday, June
29 is for your review and comment. Would you please let me know whether
this does or does not have your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 12
> Date: 6/29/2002
> Day: Saturday
> Time: 7 AM - 10 AM
> System: Building Power
> Duration: 3 hours
> Reason:
> Relocate power panel located in 12-090.
>
> Effect:
> Loss of building power, computers and lighting in Bldg. 12 during the
> 3-hour shutdown period.
>
>