[60037] in Hotline Meeting
Bldg. 36 - Compressed Lab Air Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 19 09:56:12 2002
Message-ID: <568F0AEE7A57D511923900508B556451012320C8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, Robert Cunkelman <rpc@PLANT.MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'wrgibbs@rle.mit.edu'"
<wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 19 Jun 2002 09:56:10 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: amcgurl@rle.mit.edu; B-Zone; Cust-Coach; Robert Cunkelman;
> schedule@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 36 - Compressed Lab Air Shutdown Request
>
>
The following compressed lab air shutdown request for Blg 36 - 847, 879 and
rest of 8th floor on Friday, June 21 is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 36 - 847, 879 and rest of 8th floor
> Date: 6/21/2002
> Day: Friday
> Time: 7 AM - 10 AM
> System: Compressed Lab Air
> Duration: 3 hours
> Reason:
> Demolish lab air lines for 8th floor renovation.
>
> Effect:
> Loss of compressed lab air in 36 - 8th floor during the shutdown period.
>
>