> Subject: Bldg. 7 - Heating Hot Water/Supply Heating Shutdown Request
>
>
The following heating hot water/supply heating shutdown request for Bldg. 7
- 243A and 243B Library on Monday, June 24 is for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 7-243A and 243B
> Date: 6/24/2002
> Day: Monday
> Time: 10 AM - 2 PM
> System: Heating Hot Water/Supply Heating
> Duration: 4 hours
> Reason:
> Tie-in piping for new fan coil units in 7-145.
>
> Effect:
> Loss of heating hot water (bldg. heat) and supply heating (via ceiling
> supply fans) during the shutdown period.
>
>