[59995] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 13 - Hot and Cold Lab Process Water/Lab and Acid Waste Shut

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 14 09:14:16 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232089@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'elk@mit.edu'" <elk@MIT.Edu>, "'generoso@mit.edu'" <generoso@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 14 Jun 2002 09:14:12 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; elk@mit.edu; generoso@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 13 - Hot and Cold Lab Process Water/Lab and Acid Waste
> Shutdown Request
> 
> 
The following hot and cold lab process water/lab waste and acid waste
shutdown request for Bldg. 13 - 2112 and 2096, 2091, 2099, 2111, 2112, 2128
and 2128A on Tuesday, June 18 is for your review and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 13 -  2091, 2096, 2099, 2111, 2112, 2128 and 2128A
> Date: 6/18/2002
> Day: Tuesday
> Time: 5 AM - 9 AM
> System: Hot and Cold Lab Process Water/ Lab Waste Drainage/Acid Waste
> Drainage and Helium Recovery
> Duration: 4 hours
> Reason: 
> Tie-in systems for new fume hood in 13-2119.
> 
> Effect: 
> Loss of  hot and cold lab process water (for equipment requiring use of
> same), lab waste drainage and acid waste drainage in the above-listed
> rooms during the shutdown period.
> 
> 