[59980] in Hotline Meeting
Bldg. E51 - Air Handlers 1 and 2 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 13 12:08:46 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232079@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cbates@mit.edu'" <cbates@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'graham@mit.edu'" <graham@mit.edu>, "'gwj@mit.edu'" <gwj@mit.edu>,
"'lhill@mit.edu'" <lhill@mit.edu>, "'mchin@mit.edu'" <mchin@mit.edu>,
"'mdimauro@mit.edu'" <mdimauro@mit.edu>,
"'mscoppa@mit.edu'"
<mscoppa@mit.edu>, "'mwf@mit.edu'" <mwf@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'scobb@mit.edu'" <scobb@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 13 Jun 2002 12:08:43 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: cbates@mit.edu; E-Zone; graham@mit.edu; gwj@mit.edu; lhill@mit.edu;
> mchin@mit.edu; mdimauro@mit.edu; mscoppa@mit.edu; mwf@mit.edu;
> schedule@mit.edu; scobb@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E51 - Air Handlers 1 and 2 Shutdown Request
>
>
The following Air Handlers 1 and 2 shutdown request for Bldg. E51 (all of
old building only) on Thursday, PM June 13 is for your review and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E51 - old building only
> Date: 6/13/2002
> Day: Thursday
> Time: 2 PM - 6 PM
> System: Air Handlers 1 and 2
> Duration: 4 hours
> Reason:
> Exercise and lubricate inlet vanes.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in old
> building only during the 4-hour shutdown period.
>
>