Bldg. 66 - Air Handler 1 Shutdown/Re-Install Chilled Water Coils
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 30 14:25:27 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231FAB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patsys@mit.edu'" <patsys@mit.edu>,
"'swetzel@mit.edu'"
<swetzel@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'kkgleasn@mit.edu'" <kkgleasn@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
Cust-Coach <cust-coach@mit.edu>, A-Zone
<A-Zone@mit.edu>,
Paul Stordy <PStordy@PLANT.MIT.EDU>,
Jack Allen
<jrallen@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"Larry St. John"
<lstjohn@PLANT.MIT.EDU>,
Shawn Smith <SJSmith@PLANT.MIT.EDU>
Date: Thu, 30 May 2002 14:25:24 -0400
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
The Facilities Department would like to extend the re-installation of the
chilled water coils to Air Handler 1 for Bldg. 66 - Floors 1 through 5 North
another day (to Friday, 5/31 - 7 AM - 3 PM or sooner). Would you please
advise whether this extension has your approval or does not.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance