Bldg. 3 - Compressed Control Air, Supply Cooling/Heating Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 30 08:48:37 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231F97@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'arhodes@mit.edu'" <arhodes@mit.edu>, C-Zone <C-Zone@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
        "'dfucillo@mit.edu'" <dfucillo@mit.edu>,
        "'dory@mit.edu'" <dory@mit.edu>,
        "'engler@mitvma.mit.edu'" <engler@mitvma.mit.edu>,
        "'fenner@mit.edu'"
	 <fenner@mit.edu>,
        "'gossard@mit.edu'" <gossard@mit.edu>,
        "'hlbroder@mit.edu'" <hlbroder@mit.edu>,
        "'honda@mit.edu'"
	 <honda@mit.edu>, "'ikec@mit.edu'" <ikec@mit.edu>,
        "'jobrien@mit.edu'"
	 <jobrien@mit.edu>,
        "'kimball@mit.edu'" <kimball@mit.edu>,
        "'lsandler@mit.edu'" <lsandler@mit.edu>,
        "'mamullow@mit.edu'"
	 <mamullow@mit.edu>,
        "'ndk@mit.edu'" <ndk@mit.edu>, "'placido@mit.edu'"
	 <placido@mit.edu>,
        "'psking@mit.edu'" <psking@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'sdimond@mit.edu'"
	 <sdimond@mit.edu>,
        "'smathis@mit.edu'" <smathis@mit.edu>,
        "'strohon@mit.edu'" <strohon@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 30 May 2002 08:48:32 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	arhodes@mit.edu; C-Zone; Cust-Coach; Cust-Coach; dfucillo@mit.edu;
> dory@mit.edu; engler@mitvma.mit.edu; fenner@mit.edu; gossard@mit.edu;
> hlbroder@mit.edu; honda@mit.edu; ikec@mit.edu; jobrien@mit.edu;
> kimball@mit.edu; lsandler@mit.edu; mamullow@mit.edu; ndk@mit.edu;
> placido@mit.edu; psking@mit.edu; schedule@mit.edu; sdimond@mit.edu;
> smathis@mit.edu; strohon@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 3 - Compressed Control Air, Supply Cooling/Heating
> Shutdown Request
> 
> 
The following compressed control air, supply cooling/heating shutdown
request for Bldg. 3 on Thursday, 6/6 is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 3 - entire building
> Date: 6/6/2002
> Day: Thursday
> Time: 7 AM - 11 AM
> System: Compressed Control Air, supply cooling/supply heating
> Duration: 4 hours
> Reason: 
> Replacement of control air compressor.
> 
> Effect: 
> Loss of compressed control air, supply cooling/heating during the shutdown
> period.
> 
> 