Bldgs. E17 and E18 - Steam Station Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 28 14:41:06 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231F76@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@mit.edu>, "'dreid@mit.edu'" <dreid@mit.edu>,
        E-Zone <E-Zone@mit.edu>, "'jmganno@mit.edu'" <jmganno@mit.edu>,
        "'lombardo@mit.edu'" <lombardo@mit.edu>,
        "'sdalton@mit.edu'"
	 <sdalton@mit.edu>,
        "'shyoung@mit.edu'" <shyoung@mit.edu>, "'tiki@mit.edu'" <tiki@mit.edu>,
        "'wardd@mit.edu'" <wardd@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'dudley@mit.edu'"
	 <dudley@mit.edu>,
        "'nsteele@mit.edu'" <nsteele@mit.edu>,
        "'safety@mit.edu'" <safety@mit.edu>,
        "'tquinn@mit.edu'" <tquinn@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 28 May 2002 14:40:55 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	bengel@mit.edu; dreid@mit.edu; E-Zone; jmganno@mit.edu;
> lombardo@mit.edu; sdalton@mit.edu; shyoung@mit.edu; tiki@mit.edu;
> wardd@mit.edu; shutdowns@mit.edu; dudley@mit.edu; nsteele@mit.edu;
> safety@mit.edu; tquinn@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. E17 and E18 - Steam Station Shutdown Request
> 
> 
The following Steam Station shutdown request (hot domestic, hot lab process
water and supply heating) shutdown request for Bldgs. E17 and E18 on
Saturday, 6/1 is for your information and comment.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: E17 and E18
> Date: 6/1/2002
> Day: Saturday
> Time: 7 AM - 3 PM
> System: High, medium and low pressure steam
> Duration: 8 hours
> Reason: 
> To install steam flow meter.
> 
> Effect: 
> Loss of hot domestic water (for bathroom, kitchen and lab sink faucets)
> and hot lab process water (for lab sink faucets and equipment) and supply
> heating to Air Handler 6, Air Handler 3, Air Handler 2, Air Handler 1  to
> E17 and E18 via ceiling supply fans and E17 Warm Rooms during the shutdown
> period.
> 
> 