[59759] in Hotline Meeting
FW: Case 276893: This case has recently been updated
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 23 13:10:38 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231F43@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'hotline@mit.edu'" <hotline@mit.edu>,
"'cgroves@mit.edu'"
<cgroves@mit.edu>
Date: Thu, 23 May 2002 13:10:35 -0400
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
JJ and Carrie -- Here is the response to your question from Paul Stordy
about the Athena rooms that would be affected by this shutdown request.
Please advise what you would like to do and thanks.
Andrea
-----Original Message-----
From: Paul Stordy
Sent: Wednesday, May 22, 2002 11:10 AM
To: Andrea Nichols
Subject: RE: Case 276893: This case has recently been updated
Andrea,
After investigating the Athena Clusters listed, the only room
affected (as far as we can determine) would be 11-112.
Paul
-----Original Message-----
From: Andrea Nichols
Sent: Monday, May 20, 2002 11:56 AM
To: Paul Stordy
Subject: FW: Case 276893: This case has recently been updated
Paul --
Would you please respond to JJ Morey's question below re Athena Rooms.
Thanks.
Andrea
-----Original Message-----
From: hotline@mit.edu [mailto:hotline@mit.edu]
Sent: Monday, May 20, 2002 12:29 PM
To: andrea@PLANT.MIT.EDU
Subject: Case 276893: This case has recently been updated
Case 276893 has recently been updated and stands as follows.
Please retain the case number in the subject line for future replies
connected with this case.
Most recent entry
=================
(Comment [05/20/2002 11:29:20 by jjmorey])
Hi Andrea -
I have not heard back from anyone on this.
JJ
Case History
============
Email Received [05/14/2002 13:45:23 by daemon]
Date: Tue, 14 May 2002 13:45:23 -0400
To: "'shutdowns@mit.edu'" <shutdowns@mit.edu>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc:
Subject: Bldgs. 1, 2, 3, 4, 5, 6, 7, 7A, 8, 10 & 11 Emergency Power Shutdo
wn Request
> To: shutdowns@mit.edu
> Cc:
> Subject: Bldgs. 1, 2, 3, 4, 5, 6, 7, 7A, 8, 10 & 11 Emergency Power
> Shutdown Request
>
>
The following Emergency Power shutdown request for Bldgs. 1, 2, 3, 4, 5, 6,
7, 7A, 8, 10 and 11 on Sunday, June 2 is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 1, 2, 3, 4, 5, 6, 7, 7A, 8, 10 and 11
> Date: 6/2/2002
> Day: Sunday
> Time: 6 AM - 2 PM
> System: Emergency Power
> Duration: 8 hours
> Reason:
> Cut over to new emergency panel.
>
> Effect:
> Loss of Power: access controls; emergency power, elevators, telephones
> and lighting in corridors/stairs durin the shutdown period.
>
>
Comment [05/15/2002 09:19:50 by jjmorey]
Hi Andrea
Will this shutdown effect power in the athena clusters?
1-142
1-115
2-032
2-225
4-035
4-167
10-500
10-600
11-112
Thanks
Email Sent [05/15/2002 09:19:50 by jjmorey]
(Through the web interface)
To: andrea@PLANT.MIT.EDU
Cc: